Light Gauge Steel Staircase Detailing: Stringers, Landings & Structural Connections

A comprehensive technical guide for structural engineers, detailers, and fabricators working with cold-formed steel (CFS) staircase systems. From stringer configurations and landing support details to guardrail integration and fabrication-ready shop drawings, this presentation covers the full scope of LGS staircase detailing — with a focus on code-compliant, buildable, and coordination-ready documentation.

Light Gauge Steel Staircase Detailing: Stringers, Landings & Structural Connections

LGS Staircase Systems & Stringer Configurations

Light gauge steel staircases are engineered assemblies typically built from cold-formed steel (CFS) members — most commonly C-channels, track sections, and built-up box sections. Understanding the system type and stringer configuration is the foundation of all detailing work.

Common LGS Staircase System Types

Open-Riser Stringer Systems

Stringers run parallel to the stair slope with no enclosed riser. Treads are attached directly to stringer flanges using clip angles or bent tabs. Common in utility and secondary egress stairs.

Closed-Riser Pan Systems

Steel pans welded or screwed between stringers form the riser-and-tread assembly. Pans are filled with concrete or gypsum to meet fire and load requirements. Typical in commercial multi-story applications.

Mono-Stringer (Center Stringer)

A single built-up box stringer runs along the center of the stair. Treads cantilever to both sides. Requires careful torsion analysis and robust end connections to floor structure.

Prefabricated Modular Stairs

Factory-assembled CFS stair modules shipped to site and bolted to structure. Require precise anchor bolt layouts and coordination with structural openings in the floor framing plan.

Stringer Framing & Section Selection

Stringer depth, gauge, and section type are governed by span, load, and deflection limits. Key detailing considerations include:

**Member selection:** Stringers are typically C-sections (350S or 600S series) or built-up box sections from back-to-back C members. Minimum 18-gauge for residential; 14–16 gauge for commercial applications.

**Stringer slope:** Inclined members must be detailed with plumb cuts at top and bottom bearing points. Cope depths, block-out dimensions, and bearing lengths must be explicitly called out in shop drawings.

**Lateral bracing:** Stringers are susceptible to lateral-torsional buckling. Intermediate bridging, cross-bracing, or blocking between stringers must be spaced per AISI S100 requirements — typically not exceeding 4 to 6 feet on center.

**Web stiffeners:** Required at bearing points and concentrated load locations. Stiffener sizing and attachment (screw pattern or weld) must be detailed at both the top landing connection and the bottom slab/floor bearing.

**Deflection limits:** Live load deflection is typically limited to L/360. Stringer camber or pre-deflection requirements should be noted on fabrication drawings.

All stringer designs must comply with AISI S100 (North American Specification for CFS) and applicable IBC chapter requirements for means of egress stairs.

CFS Stair Detailing

Riser, Tread, Landing
& Opening Details

Precise detailing of individual stair components and landing framing is critical for both structural performance and code compliance. Each element must be coordinated with the overall staircase geometry, the floor framing system, and the architectural finish requirements.

Tread & riser assembly

Riser & Tread Support Details

Tread attachment: Treads are secured to stringer flanges using bent clip angles (minimum 18-gauge), welded tabs, or factory-punched stringer notches. Minimum two fasteners per side—screws, bolts, or welds per the connection schedule.
Riser framing: In closed-riser systems, riser members (track or flat strap) are set plumb between stringer faces and fastened at top and bottom. Risers provide lateral stiffness to the stringer assembly and must be continuous across the full stair width.
Tread nosing: Where concrete or gypsum fill is used, a formed steel nosing angle is welded or screwed at the leading edge of each pan. Nosing projection, slip resistance, and contrast strip details must match architectural specs.
Stair geometry: Maximum riser height: 7¾ in. Minimum tread depth: 10 in. (IBC 1011.5). These must be maintained consistently throughout the flight—verify that stringer geometry produces uniform rise and run before releasing drawings.
Opening reinforcement

Reinforcement at Openings

Floor openings for stair shafts require significant reinforcement. Trimmer joists and header members must be doubled or tripled depending on the span and tributary load. All opening reinforcement members must be detailed with their own connection schedules—do not rely on generic notes. Web stiffeners are required at every header-to-trimmer intersection. Blocking panels must be installed to prevent web crippling in trimmer members adjacent to the opening.

Landing support & framing

Four Critical Landing Details

01
Landing Platform Framing
Intermediate landings are framed as independent horizontal platforms using CFS joist or track sections. Platform depth must equal or exceed the required stair width. Joist sizing is based on live load (100 psf for egress stairs per IBC) plus dead load from decking and finish.
02
Landing-to-Wall Connection
Landing frames bear on CFS wall tracks or structural ledgers. Ledger angles must be anchored to stud walls with shear-rated screws or bolts at calculated spacing. Where landings span between walls, hangers or clip angles transfer vertical reaction into the wall framing.
03
Stringer-to-Landing Node
The junction of the inclined stringer and the flat landing platform is the most critical connection in the assembly. Stringer end must be plumb-cut and fitted with a seat angle or welded end plate. The connection must transfer both vertical shear and any horizontal thrust from the inclined member. Full-depth bearing stiffeners are required on both sides of the stringer web.
04
Decking & Substrate
Landing decks typically use 18-gauge CFS deck panels, cement board, or structural sheathing. All deck-to-frame attachments must be shown in plan view with fastener type, size, and spacing. Coordinate substrate with the finish flooring specification.
Stair assembly

Detail the tread, riser, landing, and opening as one coordinated system.

Verify stair geometry, reinforce shaft openings, size landings for code loads, and explicitly detail every stringer, wall, and deck connection before fabrication.

LGS STAIR DETAILING

Structural Connections, Guardrails & Coordination

The structural connections between the staircase and the building's floor framing system — combined with properly integrated guardrail and handrail assemblies — define both the safety performance and the code compliance of any LGS stair installation. These elements must be fully detailed, not simply noted.

PART 1

Staircase-to-Floor Framing Connections

BOTTOM · slab / CMU / CFS wall
TOP · header / rim track

Top Landing Connection

The upper stringer end bears on a structural header or rim track in the floor framing. A welded seat angle or bolted end plate transfers vertical and horizontal loads.

Verify and note minimum bearing length per AISI S100 crippling provisions.

Bottom Bearing Connection

The lower stringer end typically bears on a concrete slab or CMU wall via a base angle or embedded plate. Where it bears on a CFS wall, full stud blocking and load path continuity to the foundation must be shown.

Call out anchor bolt size, spacing, and embedment depth explicitly.

Lateral Restraint

Both top and bottom connections must include lateral restraint details to prevent out-of-plane movement of the stringer.

Clip angles Kicker plates Through-bolts to adjacent structure

Differential Movement

Where the stair connects to concrete structure at one end and CFS framing at the other, details must account for differential settlement and shrinkage.

Slotted holes in connection plates allow controlled vertical movement without inducing restraint forces.
PART 2

Guardrail & Handrail Integration

POST BASE CONNECTIONS
200 lb
concentrated lateral load at top of rail · IBC 1015
Posts apply concentrated moment and shear at their base. CFS stringer flanges alone are insufficient — anchor to reinforced blocking sections, welded plates, or structural tubes running between stringers.
WALL-MOUNTED HANDRAILS
Pullout
capacity from CFS stud framing must be verified
Verify bracket spacing, fastener type, and pullout capacity. Where wall framing is insufficient, blocking between studs is required and must be shown on the stair details sheet.
RETURN & TERMINATION
34–38 in.
rail height per IBC
Rail returns at top and bottom landings must be dimensioned and shown in elevation. Coordinate rail height with finished floor elevations, not rough framing dimensions.
PART 3

Coordination with Architectural & Structural Documents

A

Architectural Coordination

Verify stair width, headroom clearance, and landing dimensions against architectural drawings before beginning detail production.

Min. headroom 80 in. · IBC 1011.3

Identify all finish materials — tile, carpet, nosing — that affect structural reveal dimensions and tread/riser geometry.

S

Structural EOR Coordination

Obtain confirmed header and trimmer member sizes from the EOR before detailing opening reinforcement.

Confirm design loads:

Live load Dead load Seismic / wind uplift

All deviations from the structural drawings must be RFI'd and resolved before fabrication.

M

MEP & Fire Protection

Stair shafts commonly contain fire suppression piping, conduit, and ventilation.

Coordinate stringer depth and opening reinforcement framing with MEP routing early to avoid costly field modifications.

Show sprinkler head locations within the stair enclosure on coordinated drawings.
THE RFI LOG

Use a formal RFI log to track all coordination questions between the stair detailer, EOR, architect, and MEP engineer.

Stair detailer EOR Architect MEP engineer

Never assume — document every design decision that affects fabrication.

Fabrication-Ready LGS Stair Shop Drawings

The final deliverable of the LGS staircase detailing process is a complete, fabrication-ready shop drawing package. These drawings must communicate all dimensional, material, and connection information needed for the fabricator to cut, assemble, and deliver the stair without returning to the engineer or detailer for clarification.

What a Complete Shop Drawing Package Includes

01

Plan & Elevation Views

Full stair plan showing width, landing dimensions, and opening location referenced to column grid or finish walls. Elevation views for each flight showing stringer slope, riser count, tread depth, landing height, and overall stair height from finish floor to finish floor. All dimensions must reference a consistent datum.

02

Stringer Detail Sheets

Stringer member size, gauge, length, and slope. Plumb cut geometry at top and bottom. Web stiffener locations, sizes, and attachment. Bridging and bracing locations with screw pattern. Hole patterns for tread clips and riser attachment. Bill of materials (BOM) for every stringer in the assembly.

03

Connection Details

Detailed sections at every unique connection node: top bearing, bottom bearing, mid-landing, guardrail post base, and wall bracket. Each detail must show member sizes, clip angle or weld sizes, fastener type (screw designation or bolt grade), spacing, and edge distances. Generic "connect per code" notes are not acceptable on fabrication drawings.

04

Material & Finish Schedule

Steel member designations (SSMA designations preferred), minimum yield strength (Fy = 33 or 50 ksi as designed), coating specification (bare, primed, galvanized, or powder-coat), and any ASTM references. Where dissimilar metals contact each other — particularly at concrete anchors — isolator requirements must be noted.

05

Approval & Revision Control

Submit drawings for EOR review and stamp prior to fabrication release. Maintain a revision cloud and revision block on every sheet. No field modifications without written authorization. As-built markups must be returned to the detailer for record drawing updates after installation.

Key Quality Benchmarks for LGS Stair Shop Drawings

Dimensional Completeness

Every member, cutout, hole, and bearing surface is fully dimensioned. No implied or assumed dimensions.

Load Path Clarity

Gravity and lateral load paths are traceable from tread to stringer to floor framing on every connection detail.

Code Traceability

AISI S100, IBC chapter and section references cited on the drawing set. Egress stair dimensions verified against IBC 1011.

Coordination Sign-Off

Architectural, structural, and MEP coordination confirmed and documented before the first fabrication cut is made.

"A shop drawing that requires a phone call to interpret is an incomplete shop drawing. Build it on paper before you build it in steel."

Investing time in thorough, coordinated LGS staircase shop drawings pays dividends at every downstream stage — fewer RFIs during fabrication, faster field installation, reduced punch list items, and a final assembly that performs exactly as the structural model predicted. For stair detailers and fabricators alike, the shop drawing package is the product.